Prologis has sold a 1 million-square-foot, Class A industrial facility in Northampton, Pa., in the Lehigh Valley area, Yardi Matrix information shows. Fluidstack, an AI compute and infrastructure data center operator company, has paid $162.9 million for the building, or about $161 per square foot.
The facility is at 2500 Liberty Drive, near State Route 329, in an area with corporate neighbors such as FedEx, DHL, Amazon and Aldi, among others.
Spanning 85 acres, the property is 6 miles away from Lehigh Valley International Airport and 10 miles from downtown Allentown, Pa. The location also offers access to U.S. Route 22 and Interstate 78, both serving as key east-west corridors connecting Northampton County to the broader eastern Pennsylvania area and toward New Jersey.
READ ALSO: 10 Emerging Data Center Markets to Watch
The property features 40-foot clear heights, 120 dock-high doors, four drive-in doors, LED motion sensors, ESFR sprinkler systems and a 5,990-square-foot office space. The facility also provided 366 car parking spots and 211 trailer parking spots.
Prologis completed the warehouse in 2023 and submitted proposal for converting it into a hyperscale data center project earlier this year.
A data center conversion
Allen Township’s Board of Supervisors unanimously approved the plans in March 2026. At the time, the property had the potential to be the first such data center project in Lehigh Valley, according to Lehigh Valley Public Media.
Plans call for repurposing the existing building and existing truck parking into a data center facility with power provided by PPL Electric Utilities, a substation, closed-loop systems and a capacity of approximately 300 megawatts.
The transaction comes as Prologis pursues new data center developments and conversions of select logistics properties into energy-ready facilities, alongside its broader industrial investments. The REIT also views data center sales as a way to recycle capital.
A similar transaction is the $750 million sale of a data center in Elk Grove Village, Ill., which GI Partners acquired from HMC Capital. Prologis converted the property into a data center in 2024 through a partnership with Skybox Datacenters.
Recent data center investments in the Mid-Atlantic
In the Mid-Atlantic region, recent transactions include Digital Realty’s $3.5 billion acquisition of ownership interests in three Northern Virginia data centers. Blackstone-affiliated funds sold their stakes in the properties, each with 96 megawatts of capacity, giving Digital Realty full ownership of the properties.
In August, Blue Owl Capital’s Stack Infrastructure paid $66.4 million for a 71-acre development site in Culpeper, Va. The property had received rezoning approval for data center development.