Data Center Financing: Show Me the Power

Energy availability, approvals and tenant credit are weighing more heavily in underwriting.

Suhail Tayyeb, clinical assistant professor at the Schack Institute of Real Estate at the NYU School of Professional Studies
Investors increasingly want proof that projects can secure power and approvals, engage local communities, attract credible customers and remain financially viable as those pieces come together, according to Tayyeb. Image courtesy of Schack Institute of Real Estate

Data center financing remains available, but a wider range of risks is shaping which projects can attract it and at what cost. Higher spreads can make it harder for owners to refinance or sell stabilized assets, while concerns about power, permitting, community opposition and tenant credit are pushing lenders and investors to look more closely at whether a project can be delivered and sustain demand.

At the same time, debate over AI’s long-term prospects is adding uncertainty. Developers can turn to CMBS, asset-backed securities, private credit, banks and project bonds across different structures, but they are not entirely independent. If investors reassess AI infrastructure risk more broadly, financing costs could rise across several channels at once.

The result may be a sharper divide between projects with contracted demand, reliable power and creditworthy tenants, and those that depend on speculative growth or less established operators.

Financing depends on execution

For lenders, a project’s scale and projected demand are no longer enough to establish that it is financeable.

“Capital increasingly needs evidence that power can actually be delivered, approvals can be obtained, communities can be engaged, customers are credible and the economics still work when all of those timelines converge,” said Suhail Tayyeb, clinical assistant professor at the Schack Institute of Real Estate at the NYU School of Professional Studies.

Jeffrey Moerdler, chair of the Data Center and Digital Infrastructure Practice at Haynes Boone
Data centers used to follow the traditional real estate adage of location, location, location, but in recent years energy has moved to the front of the line, Moendley said. Image courtesy of Haynes Boone

Power availability is one of the most immediate constraints. Jeffrey Moerdler, chair of the Data Center and Digital Infrastructure Practice at Haynes Boone and a real estate partner in the firm’s New York office, said delays in securing electricity can set projects back by years or stop them altogether.

He cited Dominion Energy’s announcement that its Northern Virginia service area had run out of available power capacity. Sites for which the utility had made contractual commitments could face delays of three to five years, while projects without power contracts could be delayed five to 10 years.


READ ALSO: Why Refinancing Is Recovering Faster Than Sales



Doug Machon, vice president of business development at Kyuden Energy Partners, a California-based third-party energy management firm that helps data centers shift from the public grid to onsite power, sees power as part of a broader execution challenge. “The projects that get built aren’t necessarily those with the best site, but those that remove uncertainty across the entire development stack,” he said.

Doug Machon, Kyuden Energy Partners VP of Business Development
Projects that address risks throughout the development process have a better chance of getting built than those relying on site advantages alone, Machon said. Image courtesy of Kyuden Energy Partners

Community opposition can create another obstacle to execution. Nearly 500 U.S. communities, including Raleigh, N.C.; Austin County, Texas, and Denver have implemented temporary moratoriums or bans on data center development to study the effects on power, water and municipal resources.

Heatmap identified 25 proposed U.S. data center projects totaling at least 4.7 gigawatts that were canceled after sustained local opposition in 2025, compared with six in 2024. Data Center Watch also identified at least 45 projects, valued at nearly $68 billion, that were blocked or delayed by local opposition in the second quarter of 2026 alone.

One example is Diode Ventures’ proposed project near Cedar Creek Lake in Texas, which faced significant concerns over water use and community impact. Diode announced it withdrew because the project would not meet the state’s evolving development standards and community expectations.


READ ALSO: Keep Your Eyes on the US Treasury


Developers are responding with measures such as trees and berms to screen facilities and reduce noise, as well as public education about data centers’ role in everyday technology and their potential economic benefits, Moerdler said. Those steps may address some local concerns, but opposition can still complicate a project’s path to approval and delivery. Tayyeb actually describes community acceptance and regulatory certainty as infrastructure: “They can be just as important to delivery as substations, transmission or fiber.”

Heatmap representing the presence of opposition groups to data centers as of the second quarter of 2026, according to Data Center Watch
This is a heatmap representing the presence of opposition groups to data centers as of the second quarter of 2026. Red to pink indicates the higher level of opposition, while blue indicates less opposition. Map courtesy of Data Center Watch

Capital is available but more selective

Despite all these execution risks, data centers continue to attract lenders and investors. National vacancy is below 1 percent and tenants are signing long-term leases for space and power, according to Carl Beardsley, senior managing director & lead of Data Center Capital Markets at JLL.

Carl Beardsley, senior managing director & lead of Data Center Capital Markets at JLL
Limited supply is pushing rents and cash flow higher, enabling lenders to finance a larger share of construction costs than in other property sectors, Beardsley told CPE. Image courtesy of JLL

“Rental rates continue to increase due to limited supply, which is increasing cash flow and allowing lenders to lend more dollars proportional to construction costs, compared to other asset classes,” Beardsley said, adding that lenders view data centers as “sticky” assets, with a low probability of tenants vacating at the end of their leases.

But the stronger demand story does not eliminate concerns about tenant quality. As the AI ecosystem evolves, projects concentrated among tenants that prove less competitive could face challenges, said Ji Zhang, senior vice president and portfolio manager at Cohen & Steers.

Established data center markets with deep and diverse tenant bases provide owners more options to backfill capacity or reposition assets as demand changes. By contrast, a development dependent on a small number of less creditworthy customers may face greater financing costs and leasing risk. That divide can affect which capital sources are willing to finance a project and on what terms.

Alternative capital is connected

Developers’ financing options span private credit, infrastructure funds, bank lending, project bonds, CMBS, ABS and corporate debt. The Structured Finance Association has noted the growing role of ABS, CMBS and private credit in meeting the sector’s capital needs.

“What matters is that these markets are not completely independent,” Tayyeb said. Investors can compare risk across them.

Beardsley noted that most stabilized data center projects are now financed through the ABS market, which had $17 billion in volume in 2025 and more than $13 billion in the first half of 2026. CMBS, including single-asset, single-borrower deals, was another source of permanent takeout financing. The market totaled $11 billion in 2025 and $6 billion in the first half of 2026.

The growth of ABS has coincided with wider spreads, but the market remains open. “It’s important to distinguish between a correction in how risk is priced and a collapse in underlying demand,” said Tayyeb.

The concern is whether investors will continue to assess each financing channel on its own terms. A recent Barclays analysis found that data center securitizations are moving more closely with hyperscaler corporate debt than with the broader ABS market. That suggests investors may increasingly view securitized data center assets as part of a larger AI infrastructure financing trade.

“Alternative capital, therefore, provides flexibility, but it does not eliminate underlying project risk,” Tayyeb said. If concerns about AI demand or tenant credit affect views of the broader trade, pressure could reach multiple financing channels.

Zhang said lenders’ reduced appetite for large-scale developments backed by non-investment-grade customers is already showing up in both financing availability and borrowing costs. So, developers may need to underwrite higher returns to compensate for more expensive capital and weaker tenant credit.

CPE Sneak Peek Newsletter Preview

CPE Sneak Peek Newsletter

Be the first to receive exclusive insights, data-backed analysis and expert commentary. Early access, every week.

Refinancing and capital recycling

Higher borrowing costs can also affect the ability to sell stabilized assets and fund new construction. Owners and developers have increasingly explored those sales as a way to recycle capital into development pipelines, Zhang noted. If buyers face more expensive financing, that could impact sale pricing and the timing of transactions.

Ji Zhang, senior vice president and portfolio manager at Cohen & Steers
According to Zhang, the central issue is whether stabilized asset valuations will align with the returns sought by investors raising capital to buy them. Image courtesy of Cohen & Steers

“We are also hearing about public and private investment vehicles being formed specifically to acquire stabilized data centers,” Zhang said, reflecting developers’ need to monetize existing assets and secure capital for new projects.

Publicly traded data center REITs may have more room to navigate changing financing conditions. Many have maintained conservative balance sheets, diversified capital sources and disciplined development pipelines relative to enterprise value. Their access to public debt and equity, private capital and joint ventures has reduced their reliance on any one source of funding. Additionally, REITs’ focus on established markets with diverse tenant demand can limit their leasing and residual-value risk.

Even with those advantages, pricing remains unsettled. “The key question is where stabilized asset valuations ultimately settle relative to the return requirements of the capital being raised to acquire them,” Zhang said.

Financing will shape what gets built

That price discovery could affect which projects advance and how quickly. The divide will not depend solely on whether a project is backed by a technology giant, Tayyeb said. Lenders will also look for contracted demand, deliverable power, entitled sites, strong counterparties and a credible execution path. S&P Global has likewise identified location, tenant demand, fiber connectivity and competitive power economics as factors affecting data center credit quality.

“I expect capital to continue flowing, but increasingly toward projects that can prove rather than merely promise execution,” Tayyeb said.

Smaller projects and emerging operators are not inherently unfinanceable, but they need to demonstrate that their plans are compelling. As Moerdler put it, lenders are asking more questions and may wait until a project “gels a little,” particularly in its early stages.

The likely result is a more selective pipeline: projects able to demonstrate execution are better positioned to secure financing, while those reliant on uncertain power, tenants or approvals may be delayed or scaled back.